ConstructSim Planner CONNECT Edition Update 5 Help

Using External Scheduling Applications

Schedules from other applications can be imported into and exported from Bentley Schedule Simulation.

Bentley Schedule Simulation supports the following file formats for import/export:

Imported Application Version Format
AstaPowerproject 11.0.01 MPX Files (*.MPX)
    Microsoft Project XML Format (*.XML)
MS Project 2003 11.0.2003 XML Format (*.XML)
MS Project 2007 12.0 XML Format (*.XML)
Primavera Project 3.1 Microsoft Project (MPX)
Primavera P6 7.0.0 Microsoft Project (XML 2007)
    Microsoft Project (XML 2002/2003)
    Microsoft Project (MPX)
Primavera P3e/c for Construction 3.5.1/4.1 Microsoft Project (MPX)
Exported Application Version Format
Asta Powerproject 11.0.01 XML, MPX
MS Project 2003 11.0.2003 XML
MS Project 2007 12.0 XML
Primavera Project 3.1 MPX
Primavera P6 7.0.0 XML, MPX
Primavera P3e/c for Construction 3.5.1/4.1 MPX


Sample of imported .txt file

Bentley Schedule Simulation supports various types of Start-Finish dates and times for tasks. These dates and times can be imported from other scheduling software packages.

When you export a schedule, you can either overwrite the original schedule or replace specific task properties in the original schedule.

However, some fields such as Early Start, Early Finish, Late Start, and Late Finish are calculated by the external scheduling software. Changes made to these fields in Bentley Schedule Simulation may be ignored when the data is imported into the scheduling package. For exchange format specifications, refer to the documentation of the third-party scheduling software application.